Problem Summary


Review MRP job times and propose solution

Admin Info


Purpose
Review MRP jobs and propose solution for the Job Changes
Requested by
Babu Lankipalli
Issue Date
08-13-2013
Resolved by
Adithya
Resolved Date
08-13-2013
Document Status
WIP

Detailed Problem Description

(Include Screen Shots if required )

MRP job running too long, review MRP job scheduled times and propose solution to MRP as separate task for all APAC plants.

Solution Analysis and Recommendations

(Include Screen Shots if required)

Attached is the document with the analysis and recommendations.

8482_MRP_Times.doc

Created/Changed variants.

Attached is the file which shows the new jobs and steps:

New_Jobs.xlsx

Resolution


Sent the Recommendations as attached.
Created New Variants for the Jobs.
The New Jobs with the steps are given in the spread sheet attached.
New_Jobs.xlsx

Created & Changed the variants